Client
Mersey & West Lancashire Teaching Hospitals — PFI (VINCI)
Contract
JCT Design & Build
Delivery
Two-Stage Procurement
Duration
Delivered within a 12-week fast-track programme

Overview

MET Healthcare were appointed as Principal Contractor to convert an existing general theatre into a new orthopaedic theatre at Whiston Hospital. The project included the installation of an Ultra-Clean Ventilation (UCV) canopy and full mechanical and electrical upgrades, all delivered within a live acute hospital environment.

Working collaboratively with VINCI and the Trust, MET completed the project on an accelerated 12-week programme, maintaining full operation of adjacent theatres throughout. The new orthopaedic theatre achieved validated UCV performance exceeding HTM 03-01 standards.

Scope of Works

Turnkey conversion of an existing general theatre into a fully compliant orthopaedic operating theatre, delivered under a two-stage JCT Design & Build contract.

Scope included:

  • Full demolition and strip-out of the existing theatre, including redundant services and finishes, completed under strict infection control measures
  • Structural alterations and formation of new openings to accommodate UCV canopy supports and fire compartmentation upgrades
  • Installation of a new UCV laminar flow canopy system validated to HTM 03-01 standards
  • Complete mechanical and electrical installations, including HVAC plant, ductwork, medical gases, IPS/UPS systems, BMS integration, lighting, nurse call, and fire alarm systems
  • Installation of specialist theatre equipment including pendants, surgical lighting, Theatre Control Panels (TCPs), PACS panels, and laser lock-down systems
  • Application of MET Healthcare’s High-Pressure Laminate (HPL) walling and ceiling systems, providing hygienic, seamless, and durable clinical finishes
  • Comprehensive commissioning, testing, and validation of all systems including ventilation, electrical, and radiation shielding in line with HTM and HBN standards
  • Phased and carefully sequenced programme ensuring continuous operation of adjacent live theatres throughout the works

Key Outcomes

  • Zero RIDDOR incidents and no downtime in adjacent live theatres.
  • UCV validation exceeded HTM 03-01 standards.
  • Completed within accelerated 12-week programme.
  • Snag-free handover and client satisfaction score: 10/10.
  • 95% waste diversion from landfill.
  • Seamless integration with existing hospital systems and CAFM platform.

Social Value

  • Economic: Local subcontractors engaged, with the majority of spend retained within the North West region.
  • Social: Collaboration with local colleges to support apprenticeship placements in electrical and mechanical trades.
  • Environmental: Energy-efficient LED task lighting and UCV canopy operation modes reduced ongoing energy demand.
  • Health & Safety: “Safety 24/7” culture embedded across all teams, achieving zero reportable incidents.